Cut Nyak Dien Kost

Located in a very prime area of Central Jakarta, this project was a milestone. Our scope is to arrange the development from A to Z. From the feasibility study, permit (land use change), design and construction. The permit itself took about more than a year parallel with the design to construction. 

​

The narrow site (6m x 35m) is a challange for the design. However it could provide 18 rooms as briefed by the feasibility study. The design intended to keep opening both left and right side of the building for the natural ventilation and the air circulation.

​

Design : 2018

Construction : 2018 - 2020

Status : Building completed